Flowmeter Installation for TSE Network – CP13 Snag Rectification

Contract Number:           TS_050

Tender No. :           PWA/GTC/101/2014-2015 & PWA/GTC/054/2017

Project Title        :           Flowmeter Installation for TSE Network – CP13 Snag Rectification

Commencement :           09-08-2020

Duration :           539 Days


Ashghal (Qatar Public Works Authority) has awarded MACE Qatar a contract for Flowmeter Installation for TSE Network – CP13 Snag Rectification.

Previous
Previous

Roads & Infrastructure in Doha Industrial Area Package 07-C311

Next
Next

Construction of Foul Sewers for Various Catchments within Doha South (DS039 & DS040) Package 2 - C826/2